1. Arkansas 60, U.S. 64, and U.S. 65B Improvements
    • Scope: Resurface approximately 9.4 miles of Arkansas 60, U.S. 64, and U.S. 65B
    • Completion Date: February 2025
    • Contractor: Rogers Group
    • Cost: $6.316 million
  2. U.S. 64 and Hogan Lane Roundabout
    • Scope: Construct Roundabout at intersection of U.S. 64 and Hogan Lane
    • Completion Date: Late 2025
    • Contractor: Rogers Group
    • Cost: $3.691 million

SOURCE: Arkansas Department of Transportation